Use these steps to schedule a time to run the updates.
- Click Schedule Update. 
- Click Create Schedule, type a schedule name, and then click OK. 
- Select the targets or groups from the Unscheduled Targets list, and then click Add. 
- Select a date and time to start the updates. Check UTC if you want to use Coordinated Universal Time, and not the time zone listed in the Time Zone field. 
- Click Save and Continue, click Done, and then click OK. If you click the X to close the window will not save the schedule. 
- The schedule details are updated in the Target Status. 
- The schedule is completed when you click Install on the Review/Install Updates screen. ![[Note]](note.png) - NOTE: If the Install button is grayed out, make sure you enter all required information on the Review/Install Updates screen. For more information, see Reviewing and installing updates. ![[Note]](note.png) - NOTE: Schedule settings might be lost if the HP SUM session is closed. HP recommends not to exit from an HP SUM session if a scheduled update has been set.